Tunnel work a year ahead of schedule

Tunnel work a year ahead of schedule
The final blast in the tunnel between Trongisvágur and Hvalba, Suðuroy, took place yesterday
Work on the Trongisvágur-Hvalba tunnel project started on 27 June last year, with an estimated project duration of two years
 
08.07.2020 - 09:34

When the new tunnel will be taken into use next February, the total project length will be one year shorter than originally planned.

In addition to the 2,524 metre-long tunnel, the project includes the construction of 2.3 kilometres of road in the Niðastabotnur area in Hvalba, along with 900 metres in the Gjánhamar area of Trongisvágur.

The estimated project cost is DKK 272 million.

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Leygardag 20. apríl
Vikan 20.apríl 2024
173982
Leygardag 20. apríl
Morgunlestur leygardagur 20. apríl 2024
173397
Fríggjadag 19. apríl
Vikuskiftið 19 apríl 2024
173966
Fríggjadag 19. apríl
Breddin: Ov nógv børn verða send av landinum
173951
Fríggjadag 19. apríl
Góðan morgun Føroyar
173942
Nýggjastu sendingar í SV
Fríggjadag 19. apríl
Veðrið
173964
Fríggjadag 19. apríl
Dagur og vika - teknmálstulkað
173933
Hósdag 18. apríl
Mett fyri minni (3:3)
173887