Extra costs due to “poor consultancy”

Extra costs due to “poor consultancy”
Contractor blames Danish consultancy firm for the additional costs of building Tórshavn’s new educational centre, Glasir
Ewald Kjølbro, the CEO of Landsverk, which oversees the construction of Glasir.
 
08.11.2018 - 11:02

Inadequate consultancy and incorrect design outlines are among the reasons why the Glasir project has gone over budget.

Ewald Kjølbro, the CEO of Landsverk (The Road Authority), which manages the construction, is blaming Danish consultancy firm BIG for the complications.

The project was initially budgeted at DKK 635m, but the provisional bill now stands at DKK 653m.

Kjølbro adds that further expenses can be expected before the construction is completed.

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Leygardag 25. apríl
Jambalaja - 250426
207562
Leygardag 25. apríl
Vikugesturin: Hví ikki eg?
207557
Leygardag 25. apríl
Vikan 25. apríl 2026
207553
Leygardag 25. apríl
Morgunlestur leygardagur 25.apríl 2026
207139
Nýggjastu sendingar í SV
Fríggjadag 24. apríl
Hallucination
207204
Fríggjadag 24. apríl
Veðrið
207539
Fríggjadag 24. apríl
Kakumiks 2 (6:7)
207533