Extra costs due to “poor consultancy”

Extra costs due to “poor consultancy”
Contractor blames Danish consultancy firm for the additional costs of building Tórshavn’s new educational centre, Glasir
Ewald Kjølbro, the CEO of Landsverk, which oversees the construction of Glasir.
 
08.11.2018 - 11:02

Inadequate consultancy and incorrect design outlines are among the reasons why the Glasir project has gone over budget.

Ewald Kjølbro, the CEO of Landsverk (The Road Authority), which manages the construction, is blaming Danish consultancy firm BIG for the complications.

The project was initially budgeted at DKK 635m, but the provisional bill now stands at DKK 653m.

Kjølbro adds that further expenses can be expected before the construction is completed.

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Leygardag 31. januar
Morgunlestur leygardagur 31.januar 2026
203271
Fríggjadag 30. januar
Vikuskiftið 30 jan 2026
203510
Fríggjadag 30. januar
EM-tíðindi 30. januar 2026
203495
Fríggjadag 30. januar
EM-tíðindi 29. januar 2026
203492
Nýggjastu sendingar í SV
Fríggjadag 30. januar
Veðrið
203507
Hósdag 29. januar
Anna Maria 1807
203450
Hósdag 29. januar
Veðrið
203446
Mánadag 26. januar
Veðrið
203256
Sunnudag 25. januar
Andaktin við Tóri Jacobsen
203189