Glasir: contractor relied on verbal deals

Glasir: contractor relied on verbal deals
The culture minister was kept in the dark about verbal agreements between contractor Landsverk and sub-suppliers
 
23.01.2019 - 15:05

Landsverk, which oversaw the construction of the Glasir college, resorted to verbal agreements with suppliers in the lead-up to the 10 August opening date. Many of the unpaid bills which have emerged recently are a consequence of these agreements, Landsverk now reveals.

The verbal agreements came as Landsverk was struggling meet the completion deadline.

Although the Ministry of Culture was notified on 5 January about DKK 30 million in unpaid bills, Parliament was not informed of this. Not until 16 days later, when culture minister Rigmor Dam resigned, was the public informed of the unpaid bills.

The new interim CEO of Landsverk, Árant Andriasson, and former CEO, Ewald Kjølbro, have both declined to comment on the matter.

See also: Minister: I was unaware of Glasir overspending

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Leygardag 4. apríl
PLÁTUPANELIÐ #39 (1977)
206615
Leygardag 4. apríl
Tvey velja páskatónleik
206614
Leygardag 4. apríl
Jambalaja - 040426
206613
Leygardag 4. apríl
Upp á tá - 030426
206605
Nýggjastu sendingar í SV
Fríggjadag 3. apríl
KAKUMiKS 2 (3:7)
206554
Fríggjadag 3. apríl
Guðstænasta úr Hoyvíkar kirkju
206597
Hósdag 2. apríl
Guðstænasta úr Havnar kirkju
206563