Tunnel drilling now into final stages

05.03.2019 - 10:27
Aktuelt
Tunnel drilling now into final stages
The final blast in the Eysturoy-Tórshavn subsea tunnel project is expected in May
 

The drilling of the Eysturoy-Tórshavn subsea tunnel is scheduled to be completed in mid-May.

On the Streymoy side, between Hvítanes and the roundabout inside the tunnel, 997 metres of drilling remain, while 406 metres remain on the Eysturoy side.

According to the contract, the Eysturoy-Tórshavn subsea tunnel is scheduled to be taken into use in 2020, and the work is going according to schedule, says project leader Teitur Samuelsen.

Translated by prosa.fo

 
Nýggjastu sendingar í ÚV
Týsdag 25. juni
Morgunlestur týsdagur 25. juni 2019
95938
Mánadag 24. juni
Norðurljóð 24. juni 2019
95985
Mánadag 24. juni
Við seyði í fjallahagan (2:4)
95974
Mánadag 24. juni
TB fór við øllum á jóansøku
95971
Nýggjastu sendingar í SV
Mánadag 24. juni
3-2
95997
Sunnudag 23. juni
Andakt við Ara Langgaard
95929
Sunnudag 23. juni
Guðstænasta í Fámjins kirkju
95931
Leygardag 22. juni
Video: 10mf, jóansøka 2019
95919
Leygardag 22. juni
Video: 5mf kvinnur, jóansøka 2019
95918