Hvalba tunnel drilling nearing halfway point

Hvalba tunnel drilling nearing halfway point
Almost 1,100 out of the total 2,500 metres have been drilled in the new Hvalba tunnel
Construction of the new tunnel between Hvalba and Trongisvágur, Suðuroy, is ahead of schedule
 
20.01.2020 - 12:22

Some 1,080 metres have been drilled into the new tunnel between Hvalba and Trongisvágur in Suðuroy.

When drilling started in August last year, workers ran into some difficulties as the compressed clay terrain was difficult to drill through, according to project leader Dánjal Pauli í Búðini, of building firm Articon.

 >> SEE ALSO Hvalba tunnel project put out to tender

But now the terrain is much easier to work with, he says, and the project is now slightly ahead of schedule.

The tunnel, whose total length will be 2,524 metres, is scheduled for completion two years from now.

In addition to the tunnel itself, 2.3 kilometres of road will be constructed in the Niðastabotnur area in Hvalba, along with 900 metres in the Gjánhamar area of Trongisvágur.

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Leygardag 2. november
Plátupanelið 021124
182991
Leygardag 2. november
Upp á tá 011124
182990
Leygardag 2. november
Jambalaja - 021124
182989
Leygardag 2. november
Vikan 2. november 2024
182974
Leygardag 2. november
Allahalgannaguðstænasta úr Havnar kirkju
182971
Nýggjastu sendingar í SV
Fríggjadag 1. november
Dagur og vika - teknmálstulkað
182920
Fríggjadag 1. november
Veðrið
182950
Hósdag 31. oktober
Kom á val 03
182906
Hósdag 31. oktober
Virðislønir M. A. Jacobsens 2024
182896