Work starting on subsea tunnel entrance

Work starting on subsea tunnel entrance
Preparations have begun on the entrance to the Runavík side of the undersea tunnel between Streymoy and Eysturoy
 
11.10.2018 - 15:20

Drilling and blasting for the tunnel entrance on the Eysturoy side of the Eysturoy tunnel will start in the coming days.

After a couple of weeks’ drillings, work will start on the concrete entrance to the tunnel.

An area of at least 100 metres will be fenced off, and warning signals will be given ahead of any blasting, according to Runavík City Council.

A total of 7,444 metres have so far been drilled of the Eysturoy tunnel, which will have a length of more than 11 km once completed.

Some 3,640 metres have been drilled from the Streymoy end, and 1,200 metres have been drilled from the roundabout south of Hvítanes, Streymoy.

A total of 980 metres have been drilled from the Runavík end.

See also: 

Hi-tech safety features in tunnels

Environmental approval for ‘polluting’ project

Plastic pollution will be kept to a minimum

Tórshavn’s tunnel access road facing major delays

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Mánadag 12. oktober
Norðurljóð 12.oktober 2026
214429
Mánadag 12. oktober
RagnarRokk. Maria Lessing um Resurgence
214015
Sunnudag 11. oktober
Bolero
214602
Sunnudag 11. oktober
Guðstænasta í Sandavágs kirkju
214601
Nýggjastu sendingar í SV
Mánadag 12. oktober
Veðrið
214655
Sunnudag 11. oktober
Møti úr Oasuni í Hoyvík
214615
Sunnudag 11. oktober
Andakt
214609
Leygardag 10. oktober
Sement 2026
214595
Fríggjadag 9. oktober
Veðrið
214576