Drilling begins on Sandoy-Streymoy subsea tunnel

Drilling begins on Sandoy-Streymoy subsea tunnel
The tunnel drilling equipment was switched on at the start of this month
About 100 metres have so far been drilled in Traðardalur, Sandoy
 
16.07.2019 - 20:11

Drilling work at the Eysturoy-Tórshavn tunnel finished last month, and the drilling equipment has now been transported to Sandoy.

The drilling on the Sandoy side started on 4 July, and 100 metres have so far been drilled.

Drilling will start on the Streymoy side early next month.

Completed in 2023

The tunnel will be ready to use in December 2023 if all goes according to plan.

It is estimated that 300-400 vehicles will be travelling through the tunnel per day.

The Sandoy tunnel will be 10.8 km long, which makes it the longest tunnel in the country.


Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Sunnudag 4. oktober
Møti í Filadelfia í Gøtu
214246
Sunnudag 4. oktober
Guðstænasta í Gøtu kirkju
214240
Leygardag 3. oktober
Plátupanelið #42 (1996)
214225
Nýggjastu sendingar í SV
Mikudag 7. oktober
Gylta gullið (5:5)
25040
Sunnudag 4. oktober
Andaktin við Jastrid á Dul Sørensen
214241
Leygardag 3. oktober
Sement 2026 (1:3)
214234
Fríggjadag 2. oktober
Pan-Arctic Vision 2026
214213
Fríggjadag 2. oktober
Dagur og vika - teknmálstulkað
214162