Tunnel work a year ahead of schedule

Tunnel work a year ahead of schedule
The final blast in the tunnel between Trongisvágur and Hvalba, Suðuroy, took place yesterday
Work on the Trongisvágur-Hvalba tunnel project started on 27 June last year, with an estimated project duration of two years
 
08.07.2020 - 09:34

When the new tunnel will be taken into use next February, the total project length will be one year shorter than originally planned.

In addition to the 2,524 metre-long tunnel, the project includes the construction of 2.3 kilometres of road in the Niðastabotnur area in Hvalba, along with 900 metres in the Gjánhamar area of Trongisvágur.

The estimated project cost is DKK 272 million.

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Sunnudag 12. mai
Bolero 12 mei 2024
174952
Sunnudag 12. mai
Guðstænasta í í Sjóvar kirkju.
174940
Leygardag 11. mai
Sending við countrytónleiki
174926
Nýggjastu sendingar í SV
Sunnudag 12. mai
Guðstænasta úr Vesturkirkjuni
174946
Fríggjadag 10. mai
Veðrið
174902
Hósdag 9. mai
Komið øll við (1:2)
174846
Hósdag 9. mai
Andakt við Theodor Eli Dam Olsen
174860