Minister: Suðuroy tunnel ready in 2030

Minister: Suðuroy tunnel ready in 2030
The subsea tunnel between the capital region and Suðuroy is expected to be completed in ten years’ time and will cost around DKK 3.4 billion
Finance and transport minister Jørgen Niclasen
 
05.02.2020 - 08:42

Preparations are underway for the Suðuroy subsea tunnel, and the project is expected to be completed in 2030, says transport minister Jørgen Niclasen. 

“We’re aiming to avoid making the same mistakes that were made with the planning of the Eysturoy and the Sandoy subsea tunnels, which was not to include details for access roads in the overall plan,” he says.

The estimated total cost of the project, including all access roads, will be DKK 3.3-3.4 billion.

 >> SEE ALSO Suðuroy subsea tunnel research shows early promise

“This is a lot of money, but once the tunnel opens, we will be saving at least DKK 90 million per year on the ferry service to and from Suðuroy,” says the minister.

DKK 5 million has been set aside this year for various preparatory work, including geological investigations, safety checks, trial drilling and a cost-benefit analysis.

“Having learned from our other tunnel projects, we know now that by preparing properly, we will be in a strong position to start drilling as soon the Sandoy subsea tunnel project is completed.”


Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Leygardag 28. februar
Morgunlestur leygardagur 28.februar 2026
204600
Fríggjadag 27. februar
RagnarRokk:Marius Karlsen um Obsidian Cult
204924
Fríggjadag 27. februar
Breddin: Politisku ungmannafeløgini og valini
204931
Fríggjadag 27. februar
Beinleiðis úr Studio 5 - Adrenaline
204922
Nýggjastu sendingar í SV
Leygardag 28. februar
Anna Maria 1807 - teknmálstulkað
204955
Fríggjadag 27. februar
Dagur og vika - teknmálstulkað
204954
Fríggjadag 27. februar
Veðrið
204947
Fríggjadag 27. februar
Dagur og vika - teknmálstulkað
204916
Hósdag 26. februar
Brellbiti: Hoydalar
204735