Tunnel work a year ahead of schedule

Tunnel work a year ahead of schedule
The final blast in the tunnel between Trongisvágur and Hvalba, Suðuroy, took place yesterday
Work on the Trongisvágur-Hvalba tunnel project started on 27 June last year, with an estimated project duration of two years
 
08.07.2020 - 09:34

When the new tunnel will be taken into use next February, the total project length will be one year shorter than originally planned.

In addition to the 2,524 metre-long tunnel, the project includes the construction of 2.3 kilometres of road in the Niðastabotnur area in Hvalba, along with 900 metres in the Gjánhamar area of Trongisvágur.

The estimated project cost is DKK 272 million.

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Mánadag 9. november
RagnarRokk: Morten Toft Hansen um Prisoner
215801
Mánadag 9. november
Møti hjá Brøðrasamkomuni við Tjarnir
216106
Sunnudag 8. november
Guðstænasta í Viðareiðis kirkju
216081
Sunnudag 8. november
Filosofiskur 7. partur
216049
Nýggjastu sendingar í SV
Sunnudag 8. november
Bygdarlív 3 - Skálavík
216096
Sunnudag 8. november
Hondbóltur: Montenegro - F'øroyar
216095
Sunnudag 8. november
Møti hjá Heimamissiónini við Tjarnir
216089
Sunnudag 8. november
Andaktin við Anju Bjerkenes
216083