Tunnel work a year ahead of schedule

Tunnel work a year ahead of schedule
The final blast in the tunnel between Trongisvágur and Hvalba, Suðuroy, took place yesterday
Work on the Trongisvágur-Hvalba tunnel project started on 27 June last year, with an estimated project duration of two years
 
08.07.2020 - 09:34

When the new tunnel will be taken into use next February, the total project length will be one year shorter than originally planned.

In addition to the 2,524 metre-long tunnel, the project includes the construction of 2.3 kilometres of road in the Niðastabotnur area in Hvalba, along with 900 metres in the Gjánhamar area of Trongisvágur.

The estimated project cost is DKK 272 million.

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Fríggjadag 3. mai
Vikuskiftið 3 mei 2024
174604
Fríggjadag 3. mai
Tá Grønland bjargaði Føroyum (4:6)
174593
Fríggjadag 3. mai
«Alt mítt er títt, og títt er mítt»
174541
Fríggjadag 3. mai
Morgunlestur fríggjadagur 3. mai 2024
174293
Nýggjastu sendingar í SV
Fríggjadag 3. mai
Veðrið
174592
Hósdag 2. mai
Dagur og vika - teknmálstulkað
174537
Mikudag 1. mai
Dagur og vika - teknmálstulkað
174444