Tunnel drilling now into final stages

Tunnel drilling now into final stages
The final blast in the Eysturoy-Tórshavn subsea tunnel project is expected in May
 
05.03.2019 - 10:27

The drilling of the Eysturoy-Tórshavn subsea tunnel is scheduled to be completed in mid-May.

On the Streymoy side, between Hvítanes and the roundabout inside the tunnel, 997 metres of drilling remain, while 406 metres remain on the Eysturoy side.

According to the contract, the Eysturoy-Tórshavn subsea tunnel is scheduled to be taken into use in 2020, and the work is going according to schedule, says project leader Teitur Samuelsen.

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Mikudag 14. januar
Dansival
202653
Mikudag 14. januar
Skratsj 14. januar 2026
202650
Mikudag 14. januar
Ring munnrøkt kann elva til sjúku
202655
Nýggjastu sendingar í SV
Mikudag 14. januar
Dagur og vika - teknmálstulkað
202632
Týsdag 13. januar
Veðrið
202610
Týsdag 13. januar
Dagur og vika við 3-2 - teknmálstulkað
202571
Mánadag 12. januar
Veðrið
202554
Sunnudag 11. januar
Guðstænasta úr Fuglafjarðar kirkju
202498