Tunnel drilling now into final stages

Tunnel drilling now into final stages
The final blast in the Eysturoy-Tórshavn subsea tunnel project is expected in May
 
05.03.2019 - 10:27

The drilling of the Eysturoy-Tórshavn subsea tunnel is scheduled to be completed in mid-May.

On the Streymoy side, between Hvítanes and the roundabout inside the tunnel, 997 metres of drilling remain, while 406 metres remain on the Eysturoy side.

According to the contract, the Eysturoy-Tórshavn subsea tunnel is scheduled to be taken into use in 2020, and the work is going according to schedule, says project leader Teitur Samuelsen.

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Týsdag 30. desember
Eitt korter við kórtónleiki
202067
Týsdag 30. desember
Morgunlestur týsdagur 30.desember 2025
201926
Mánadag 29. desember
Mono - seinasta av trimum sendingum
202055
Mánadag 29. desember
Morgunlestur mánadagur 29.desember 2025
201925
Nýggjastu sendingar í SV
Mánadag 29. desember
Veðrið
202051
Sunnudag 28. desember
Andaktin
202020
Sunnudag 28. desember
Møti úr Kelduni.
202023
Fríggjadag 26. desember
Upp á gólv annað jólakvøld 2025
201866
Fríggjadag 26. desember
Javnaguðstænasta úr Glyvra kirkju
201983