Tunnel work a year ahead of schedule

Tunnel work a year ahead of schedule
The final blast in the tunnel between Trongisvágur and Hvalba, Suðuroy, took place yesterday
Work on the Trongisvágur-Hvalba tunnel project started on 27 June last year, with an estimated project duration of two years
 
08.07.2020 - 09:34

When the new tunnel will be taken into use next February, the total project length will be one year shorter than originally planned.

In addition to the 2,524 metre-long tunnel, the project includes the construction of 2.3 kilometres of road in the Niðastabotnur area in Hvalba, along with 900 metres in the Gjánhamar area of Trongisvágur.

The estimated project cost is DKK 272 million.

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Fríggjadag 11. juli
Praktikanturin: Erika Hentze Niclasen
194337
Fríggjadag 11. juli
Radio Stjernekilde II - part 5
194323
Fríggjadag 11. juli
RagnarRokk: Oskar Holldorff um Shards
194118
Fríggjadag 11. juli
Morgunlestur fríggjadagur 11.juli 2025
194083
Nýggjastu sendingar í SV
Fríggjadag 11. juli
Veðrið
194338
Mikudag 9. juli
Dagur og vika - teknmálstulkað
194245
Týsdag 8. juli
Veðrið
194213
Sunnudag 6. juli
Og ein summardag (2:2)
194098