Tunnel work a year ahead of schedule

Tunnel work a year ahead of schedule
The final blast in the tunnel between Trongisvágur and Hvalba, Suðuroy, took place yesterday
Work on the Trongisvágur-Hvalba tunnel project started on 27 June last year, with an estimated project duration of two years
 
08.07.2020 - 09:34

When the new tunnel will be taken into use next February, the total project length will be one year shorter than originally planned.

In addition to the 2,524 metre-long tunnel, the project includes the construction of 2.3 kilometres of road in the Niðastabotnur area in Hvalba, along with 900 metres in the Gjánhamar area of Trongisvágur.

The estimated project cost is DKK 272 million.

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Fríggjadag 9. januar
LEITISSTEIN 09.01.2026
202450
Fríggjadag 9. januar
RagnarRokk: Toumas Hirvonen um Icemelter
202428
Fríggjadag 9. januar
Beinleiðis úr Studio 5 - Tunghoyrt
202426
Fríggjadag 9. januar
Morgunlestur fríggjadagur 9.januar 2025
202091
Nýggjastu sendingar í SV
Fríggjadag 9. januar
Dagur og vika - teknmálstulkað
202429
Hósdag 8. januar
Margreta - teknmálstulkað
202400
Hósdag 8. januar
Veðrið
202397
Mikudag 7. januar
Dagur og vika - teknmálstulkað
202341
Týsdag 6. januar
Upp á gólv á trettanda
202324