Work starts on Dalur tunnel

Work starts on Dalur tunnel
Transport minister Heðin Mortensen will dig the first sod of soil on the Húsavík side of the new Sandoy tunnel this afternoon
 
16.05.2019 - 07:40

Work to drill a tunnel between Húsavík and Dalur, Sandoy starts today at 4pm. The tunnel will be 2,200 metres long and eight metres wide.

In addition to the tunnel, 200 metres of road will be constructed on the Húsavík side and 100 metres on the Dalur side. Three kilometres of the existing road will be widened.

The project costs are estimated at DKK 75-85 million, and the tunnel will be completed in four years’ time if everything goes according to plan.

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Leygardag 19. september
Jambalaja - 190926
213511
Leygardag 19. september
Upp á tá - 180926
213505
Fríggjadag 18. september
Vikuskiftið 18 sept 2026
213496
Fríggjadag 18. september
LEITISSTEIN 18.09.2026 (Regin Guttesen)
213490
Fríggjadag 18. september
Breddin: Sjúk mentan í løgtinginum?
213475
Nýggjastu sendingar í SV
Fríggjadag 18. september
Veðrið
213493
Fríggjadag 18. september
Dagur og vika - teknmálstulkað
213473
Hósdag 17. september
Veðrið
213424
Týsdag 15. september
Dagur og vika - teknmálstulkað
213311
Týsdag 15. september
Veðrið
213303