Work starts on Dalur tunnel

Work starts on Dalur tunnel
Transport minister Heðin Mortensen will dig the first sod of soil on the Húsavík side of the new Sandoy tunnel this afternoon
 
16.05.2019 - 07:40

Work to drill a tunnel between Húsavík and Dalur, Sandoy starts today at 4pm. The tunnel will be 2,200 metres long and eight metres wide.

In addition to the tunnel, 200 metres of road will be constructed on the Húsavík side and 100 metres on the Dalur side. Three kilometres of the existing road will be widened.

The project costs are estimated at DKK 75-85 million, and the tunnel will be completed in four years’ time if everything goes according to plan.

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Sunnudag 25. oktober
Bolero 25. oktober 2026
215336
Sunnudag 25. oktober
Guðstænasta í Havnar kirkju
215335
Leygardag 24. oktober
Jambalaja - 241026
215314
Leygardag 24. oktober
LEITISSTEIN 23.10.26
215313
Nýggjastu sendingar í SV
Sunnudag 25. oktober
Bygdarlív 2 - Porkeri
215341
Sunnudag 25. oktober
Andakt
215339
Sunnudag 25. oktober
Guðstænasta í Havnar kirkju
215334
Leygardag 24. oktober
Sement-finalan 2026
215329