New college DKK 46m over budget

New college DKK 46m over budget
The Finance Committee has asked the culture minister to clarify the financial difficulties facing the new Glasir educational centre in Tórshavn
 
26.11.2018 - 12:09

Despite the contractor insisting there would be no extra costs, the construction of Glasir college has gone DKK 46 million over budget. First came an application for a DKK 18.7 million additional grant. The additional grant was subsequently increased to DKK 28.4 million. And a further application for another DKK 17.6 million is set to be submitted soon.

The Finance Committee has called a meeting with culture minister Rigmor Dam tomorrow, asking her to clarify the financial situation.

The Ministry of Culture has confirmed that all bills associated with the construction of Glasir have now been received.

Glasir, located in Marknagil, Tórshavn, is the largest on-land construction project in the country’s history.

 

See also:

Extra costs due to “poor consultancy”

Stylish educational centre opens

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Fríggjadag 24. apríl
Vikuskiftið 24 apríl 2026
207545
Fríggjadag 24. apríl
LEITISSTEIN 24.04.2026 (Wolfgang)
207536
Fríggjadag 24. apríl
Beinleiðis úr Studio 5 - Gjáir
207518
Fríggjadag 24. apríl
Morgunlestur fríggjadagur 24.apríl 2026
207138
Nýggjastu sendingar í SV
Fríggjadag 24. apríl
Hallucination
207204
Fríggjadag 24. apríl
Veðrið
207539
Fríggjadag 24. apríl
Kakumiks 2 (6:7)
207533