New college DKK 46m over budget

New college DKK 46m over budget
The Finance Committee has asked the culture minister to clarify the financial difficulties facing the new Glasir educational centre in Tórshavn
 
26.11.2018 - 12:09

Despite the contractor insisting there would be no extra costs, the construction of Glasir college has gone DKK 46 million over budget. First came an application for a DKK 18.7 million additional grant. The additional grant was subsequently increased to DKK 28.4 million. And a further application for another DKK 17.6 million is set to be submitted soon.

The Finance Committee has called a meeting with culture minister Rigmor Dam tomorrow, asking her to clarify the financial situation.

The Ministry of Culture has confirmed that all bills associated with the construction of Glasir have now been received.

Glasir, located in Marknagil, Tórshavn, is the largest on-land construction project in the country’s history.

 

See also:

Extra costs due to “poor consultancy”

Stylish educational centre opens

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Mikudag 18. september
Góðan morgun Føroyar
180846
Mikudag 18. september
Morgunlesturin mikudagur 18. september 2024
180550
Týsdag 17. september
Samværi 041 - Hvat sær gestsins eyga?
180543
Nýggjastu sendingar í SV
Mikudag 18. september
Dagur og vika - teknmálstulkað
180838
Týsdag 17. september
Veðrið
180822
Mánadag 16. september
Dagur og vika við 3-2 - teknmálstulkað
180769
Mánadag 16. september
3-2 (16. september 2024)
180768
Sunnudag 15. september
Møti úr Hebron í Leirvík
180712