Road authority boss withheld crucial information

Road authority boss withheld crucial information
Former Landsverk CEO did not inform the government that the asphalt plant near Tórshavn needed DKK 14m for urgent repairs
 
30.10.2019 - 09:03

The asphalt plant at Sund, Streymoy, which has so far cost the taxpayer DKK 33 million, will cost at least DKK 14 million more.

This is revealed in a condition report, which Ewald Kjølbro, the former CEO of road and tunnel authority Landsverk, received a few months prior to Landsverk signing a binding deal to purchase the plant.

The report included information on all of Landsverk’s activities, but Kjølbro decided to remove this information about the asphalt plant from the report before it was forwarded to the Ministry of Transport for assessment.

Purchase or rental agreement

The reason for the omission, according to Kjølbro, is that the asphalt plant was part of a regular tenancy agreement for Landverk at the time, and as such is irrelevant to the general description of the company’s activities.

The decision to omit the information about the extra costs came after two reminders from the National Audit Office that the rental agreement in reality was a purchase deal.

According to the report, a further DKK 14 million in repair costs are needed for the plant to continue its daily operations.


Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Leygardag 27. apríl
Jambalaja - 270424
174253
Leygardag 27. apríl
Upp á tá - 260424
174252
Leygardag 27. apríl
Vikan 27.apríl 2024
174245
Leygardag 27. apríl
Morgunlestur leygardagur 27. apríl 2024
173999
Nýggjastu sendingar í SV
Fríggjadag 26. apríl
Andakt við Róland í skorini
174236
Hósdag 25. apríl
Closed for Maintenance - á fimta sinni
174178
Týsdag 23. apríl
Veðrið
174126
Týsdag 23. apríl
3-2
174101
Týsdag 23. apríl
Dagur og vika við 3-2 - teknmálstulkað
174098