Hvalba tunnel drilling nearing halfway point

Hvalba tunnel drilling nearing halfway point
Almost 1,100 out of the total 2,500 metres have been drilled in the new Hvalba tunnel
Construction of the new tunnel between Hvalba and Trongisvágur, Suðuroy, is ahead of schedule
 
20.01.2020 - 12:22

Some 1,080 metres have been drilled into the new tunnel between Hvalba and Trongisvágur in Suðuroy.

When drilling started in August last year, workers ran into some difficulties as the compressed clay terrain was difficult to drill through, according to project leader Dánjal Pauli í Búðini, of building firm Articon.

 >> SEE ALSO Hvalba tunnel project put out to tender

But now the terrain is much easier to work with, he says, and the project is now slightly ahead of schedule.

The tunnel, whose total length will be 2,524 metres, is scheduled for completion two years from now.

In addition to the tunnel itself, 2.3 kilometres of road will be constructed in the Niðastabotnur area in Hvalba, along with 900 metres in the Gjánhamar area of Trongisvágur.

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Hósdag 28. november
Breddin: Fráflyting í søguligum høpi
184289
Hósdag 28. november
Morgunlestur hósdagur 28.november 2024
184107
Mikudag 27. november
Dansival á Nordlekfundi
184250
Mikudag 27. november
Skratsj 27. novembur 2024
184248
Mikudag 27. november
Andarblak - Hvør sín og tó
184233
Nýggjastu sendingar í SV
Hósdag 28. november
Kanst tú siga farvæl? (1:2)
184255
Mikudag 27. november
Kanst tú siga farvæl? (2:2)
184254
Mikudag 27. november
Dagur og vika - teknmálstulkað
184234
Mikudag 27. november
Fólksins rødd 4:4 - teknmálstulkað
184221
Týsdag 26. november
Føroysk fiktión (2:5)
184205

Annað frá KVF