Hvalba tunnel drilling nearing halfway point

Hvalba tunnel drilling nearing halfway point
Almost 1,100 out of the total 2,500 metres have been drilled in the new Hvalba tunnel
Construction of the new tunnel between Hvalba and Trongisvágur, Suðuroy, is ahead of schedule
 
20.01.2020 - 12:22

Some 1,080 metres have been drilled into the new tunnel between Hvalba and Trongisvágur in Suðuroy.

When drilling started in August last year, workers ran into some difficulties as the compressed clay terrain was difficult to drill through, according to project leader Dánjal Pauli í Búðini, of building firm Articon.

 >> SEE ALSO Hvalba tunnel project put out to tender

But now the terrain is much easier to work with, he says, and the project is now slightly ahead of schedule.

The tunnel, whose total length will be 2,524 metres, is scheduled for completion two years from now.

In addition to the tunnel itself, 2.3 kilometres of road will be constructed in the Niðastabotnur area in Hvalba, along with 900 metres in the Gjánhamar area of Trongisvágur.

 

Translated by prosa.fo

Er kopiera
Nýggjastu sendingar í ÚV
Hósdag 21. mai
RagnarRokk 21.mai 2026
208248
Hósdag 21. mai
Nýtt ljóð
208688
Nýggjastu sendingar í SV
Hósdag 21. mai
Veðrið
208691
Mikudag 20. mai
Bygdin og bjørgini 3:3
202604
Mikudag 20. mai
Dagur og vika - teknmálstulkað
208611
Týsdag 19. mai
Veðrið
208590